In addition to
being known for the Bulls and Bears (who did
quite well this year), deep-dish pizza, the Magnificent
Mile and extreme weather, Chicago also is known
for its world-renowned museums, such as the Field
Museum of Natural History, Art Institute of Chicago
and Shedd Aquarium. A museum that often is overlooked,
despite its 60,000 visitors per year, is the
Oriental Institute Museum, which is part of The
University of Chicago.
 |
Photos courtesy of CertainTeed
Corp., Valley Forge, Pa. |
The Oriental Institute
is a museum and research organization that focuses
on the ancient Near East. The institute's building
was built in 1931 and houses galleries; artifact
storage and museum archive sections; a conservation
laboratory; archaeological study areas; space
for seminars, docent events and public programs;
and professors' offices. Since 1996, the building
has been under construction for renovation and
expansion projects, but it was occupied during
the work. In 1999, the building's roof system
began to leak into the museum's reading room
and other areas. Upon inspection by NRCA member
INSPEC Inc., Milwaukee, it was discovered that
the problem wasn't the existing clay tile roof
system. Instead, it was determined the 3 1/2-inch-
(87.5-mm-) thick concrete deck, which was bowing,
was the source of the leaks.
NRCA
member Knickerbocker Roofing and Paving Co.
Inc., Harvey, Ill., took
on this high-profile project. The company's crew
members removed the existing clay tile roof system
and precast concrete roof deck panels that total
28,000 square feet (2520 m²). The company modified
existing structural deck supports and installed
a new 18-gauge steel roof deck, as well as a
tile roof system. The Oriental Institute also
features low-slope single-ply roof systems totaling
6,000 square feet (540 m²), which Knickerbocker
Roofing and Paving removed and replaced.
 |
 |
Knickerbocker
Roofing and Paving Co. Inc., Harvey,
Ill., installed
280 squares (2520m²) of clay tile. |
"This is the first
building on campus that ever had to have its
complete roof assembly removed and replaced," says
Barry O'Quinn, supervisor of sheet-metal, roofing,
masonry and recycling facility services at The
University of Chicago. "Removing all the prestressed
concrete panels and installing a new metal
deck for the clay tile roof assembly on a building
that houses irreplaceable artifacts is not
your
everyday project."
Completing
this job meant roofing crews would have to
stay out
of the way of museum patrons, students, professors
and researchers—the Oriental Institute could
not close during roof system replacement work
because of financial considerations. And crew
members were happy to oblige.
"The museum staff
and University of Chicago personnel hardly were
aware of our presence," says Chris Cronin, president
of Knickerbocker Roofing and Paving. "Many people
commented about how unobtrusive such a large-scale
project was to them."
The
10 to 12-person roofing crew also would have
to take extra safety
precautions and, obviously, could not damage
the institute's collection of artifacts dating
back to 6800 B.C.
Collections
The
Oriental Institute was founded in 1919 as part
of The University
of Chicago and headed by Henry Breasted, the
first American to receive a Ph.D. in Egyptology.
Breasted wanted to establish an institute that
would trace ancient people's progress toward
civilization—before Greek and Roman civilizations
thrived. John D. Rockefeller Jr. supported Breasted's
vision and funded the start of the institute.
Since its establishment,
the institute has sponsored archeological and
survey expeditions in every Near East country
to document and study the areas' languages, histories
and cultures. Today, the Oriental Institute has
field projects occurring in Egypt, Iraq, Israel,
Jordan and Syria. The institute also conducts
research projects in Chicago, such as developing
dictionaries and lexicons of ancient Akkadian,
Hittite, Demotic, Egyptian and Sumerian.
The
institute's collection consists of 110,000
registered objects,
165,000 photographs, and 250 cubic feet (7.5
m³) of documents and other archival material.
To house the collection, the institute has been
under renovation since 1996 to build a new wing,
storage facility and three new galleries; the
work is expected to be completed by this fall.
The Joseph and Mary Grimshaw Egyptian Gallery
and Persian Gallery, which were closed while
being renovated, reopened during 1999 and 2000,
respectively. Three additional galleries will
open at the museum and feature objects from Israel
and Palestine, Syria and Anatolia, and Mesopotamia
and Nubia.
The Persian Gallery
features objects from 6800 B.C. to 1000 A.D.
from modern Iran. In its exhibit are objects
from the Persepolis ruins (a city that thrived
from 520 B.C. to 331 B.C. and was destroyed by
Alexander the Great), glazed ceramics from the
early Islamic period, and evidence of administrative
practices and record-keeping systems from Chogha
Mish, Iran.
"The Persian Empire
was remarkable," says Matthew Stopler, a John
A. Wilson professor of Oriental studies and an
expert on Persia. "It stretched virtually over
a continent from Greece to Afghanistan and from
Egypt to Libya to western India."
The Egyptian gallery
features objects from the Predynastic Period
(5000 B.C.) to the Arab conquest in the seventh
century. The gallery includes 800 objects, such
as a 7 1/3-foot- (2.2-m-) tall statue of King
Tutankhamen found in Medinet Habu in 1931.
Ruins
Roofing work began
on the Oriental Institute in June 2000 and ended
in August 2001. Because of weather conditions,
work stopped from December 2000 through February
2001.
Before crews could
begin the tear-off process, safety precautions
had to be taken. According to Cronin, the entire
building was surrounded with scaffolding and
a safety net was assembled in the attic. The
safety net was erected not only to protect workers
but also the institute's library ceiling, which
is made of hand-painted plaster. Unfortunately,
this delicate area was the site of pre-existing
leaks.
The tile roof system
tear-off process began by removing existing tiles,
membranes, sheet-metal flashings, gutters and
precast concrete deck panels to the sloped steel
structure. Knickerbocker Roofing and Paving's
crew members removed 1,800 precast concrete roof
deck panels. To accomplish this job, a 60-ton
(54.4-Mg) crane was used.
"Typically, we
took off 6 squares (54 m²) a day," Cronin says. "The
tile and underlayment came off fairly easily,
and we used a crane to pull off the concrete
slabs."
Because the museum
still was open and university traffic swarmed
around the building, crew members were confined
to a restricted work area and roof access. In
addition, they had to protect a landmark—and
rather unique—university tree that partially
grew perpendicular to the ground. The tree has
become a symbol for university alumni; those
who return to campus often have their pictures
taken sitting on it.
Tile
work
After the tear-off
was complete, new 1 1/2-inch- (37.5-mm-) deep
18-gauge galvanized steel deck material, 12-gauge
galvanized iron metal angles, and ASTM A36-approved
steel channels and plates were installed.
Next, one layer
of 5/8-inch- (15.6-mm-) thick Dens-Deck® and
one layer of 3/4-inch- (18.8-mm-) thick plywood
were mechanically attached. Then, one ply of
self-adhering Grace Ice and Water Shield was
installed followed by two plies of No. 30 asphalt
felt that was secured by 1-inch (25-mm) diameter
head disk nails. Finally, interlocking Ludowici
Classic™ Tiles in Clay Red were laid in place.
 |
The
Oriental Institute, Chicago, features
a new Ludowici Classic™ Tile
roof system. |
Once the roof system
was installed, new steel angle gutter supports
and dimensional wood blocking that was tapered
to provide a 1/16-in-12 (0.3-degree) slope were
installed. Then, lead-coated fascia, caps, gutters
and flashings were installed at the eaves.
Additional plies
of self-adhering underlayment were installed
at the vertical transitions as an additional
membrane flashing to the metal flashing. To finish
the drainage system, new 4-inch (100-mm) diameter
copper pipes were sealed into existing cast-iron
drain leaders with liquid hot lead and soldered
into new gutters. At the end of each day, completed
work was made watertight with temporary tie-ins.
The Oriental Institute
had a unique idea for raising additional money
during tile roof replacement work. The institute
allowed 250 of the new 15,000 clay roof tiles
to be inscribed with a message to the ancient
gods written in ancient languages, such as Babylonian.
Oriental Institute
faculty, friends and university staff could write
a personal message, such as "Anna wants the gods
to heal her back," as one inscriber wrote. Others
could choose from three suggested ancient blessings,
such as "Come, O Storm God of Nerik, bring down
from heaven your gentle rain!" The message was
written in Hittite. All messages were written
on the face-down side of the panels so they do
not affect the roof's aesthetics.
Tim Cashing, director
of development for the Oriental Institute, told
the Chicago Tribune, "The exact placement
of the tiles will remain a mystery known only
to the [roofing workers] and, perhaps, the ancient
deities invoked in the blessings."
Low-slope
work
The Oriental Institute
building also consists of low-slope roof areas.
After materials on the areas were removed to
the roof deck, a new insulation system was installed.
The system consists of a base layer of 1 1/2-inch-
(37.5-mm-) thick polyisocyanurate and 5/8-inch-
(15.6-mm-) thick Dens-Deck, which was taped at
the seams. The insulation and Dens-Deck were
set in Insta-Stik low-rise foam adhesive. To
accommodate the system, new dimensional wood
blocks were added to the roof areas' perimeter
edges.
The new two-ply
Stress Ply E membrane was set in Weather King
cold-applied asphalt. The asphalt was allowed
to flash off before the membrane was rolled in
place. Next, a modified aggregate cap sheet was
installed.
Some areas of the
low-slope roof systems were small (about 200
square feet [18 m²]) and difficult to access,
and the roof system designer was concerned about
asphalt displacement from foot traffic in these
areas. To eliminate this concern, the two-ply
membrane, cap sheet, base flashings and aggregate
surfacing were not installed on the same day.
Nick
of time
Staying on schedule
is an important part of every project. But Knickerbocker
Roofing and Paving had to finish its work before
some tombs came rolling into town. An exhibit,
Treasures from the Royal Tombs of Ur, took place
at the institute during October 2001. Because
roofing work was completed on time, the Mesopotamian
artifacts could be prominently displayed in their
new temperature-controlled and leak-proof home.
"I know it sounds
as if they paid me to say this, but the reality
is that for this project to have been completed
on [The University of Chicago's] campus and for
me to only have [received] minor complaints in
the project's two-year time period is a miracle
in itself," O'Quinn says. "[The project] could
not have gone better and has become the blueprint
for how other major roof assemblies will be replaced
on campus."
Looking back on
the project, Cronin is proud of his company's
work.
"The level of pride
experienced by everyone involved in this project
from our roofing and sheet-metal workers to our
support and office personnel [is rewarding]," Cronin
says.
But Cronin and
Knickerbocker Roofing and Paving's personnel
acknowledge that the job was successful because
they received full cooperation from everyone
involved.
"The extent of
cooperation among the building owner, architect/engineer
and our employees made this project unique," Cronin
adds.
Kate Gawlik
is associate editor of Professional Roofing magazine.
Reprinted with the permission of Professional
Roofing Magazine
Project name: Oriental Institute Museum
Project location: Chicago
Roof system type: Clay tile
Roofing contractor: Knickerbocker
Roofing and Paving Co. Inc., Harvey, Ill.
Tile manufacturer: Ludowici
Roof Tile, New Lexington, Ohio